AN INTRODUCTION :
-
In todays
high labour cost concrete block are the real answer for the builders to
cut down labour cost to quicken construction
-
The principle
of this machine is egg laying type. The machine lays the blocks on concrete
floor and moves forward
-
The blocks
are left at its original position for 24 hours approximately and then sent
for curing. curing is mostly done in water tank
-
The blocks
can be sold in the market after curing about 14 to 28 days
-
Steam
curing method can also be adopted
|
SPECIFICATIONS :
| Power |
5.0
H.P. 3-Phase |
| Ramming |
3.0
H.P. |
| Vibrator |
1.5
H.P. |
| Propeltion |
0.5
H.P. |
| Moulded Area |
860
x 600 mm |
| Capacity |
2000-2200
Blocks / 8 hours
(Size
300 x 200 x 150 mm) |
| Vibrations |
5500-6000
Hz Amplitude Adjustable |
| Drive |
20
: 1 (worm reduction gear box) |
| Dimensions |
L
1950 x W 1400 x H 2000 mm |
|
Above
mentioned specifications are likely to be changed for improvement of machine
|